Most boards start with due dates only. That is enough to know what is late, and not enough to know whether the project will finish on time. A due date says when something should end. A plan also says when it has to start, and which dates cannot move.
This post takes the Website Relaunch project from the Northwind Studio demo workspace (a fictional studio and a fictional client) and turns its due dates into a plan with the Timeline view. Nothing new is created: the timeline is a third view of the tasks already on the board.
What the timeline draws
Open a project and choose Timeline next to Board and List. Each task with dates becomes a bar; the rules are short.
| On the task | On the timeline |
|---|---|
| A start date and a due date | A bar from one to the other, labelled with the assignee |
| The milestone flag | A diamond on the task’s date |
| Due date in the past, task not done | The bar is red |
| Task completed | The bar is green |
| No dates | The task is listed as unscheduled instead of being hidden |
A vertical line marks today, and the scale switches between weeks and months. Tasks stay grouped by their board column, so you can still tell what is in progress from what has not started.

Step 1: mark the dates that cannot move
Start from the end. Harbor & Finch, the client, has two fixed dates: the beta opens to their customers on 22 November and the site launches publicly on 6 December. Each is a task with the Milestone box ticked in the task panel. A milestone has no duration, so it is drawn as a diamond.
Keep milestones rare. If every task is a milestone, the diamonds stop meaning anything. Two for a six-week project is about right.
Step 2: give every task a start date
For each task, ask one question: given the due date, when does this have to start for that to be realistic? “Checkout flow redesign” is eight story points and is due on 15 November, so it started on 6 November. “Set up redirects from old URLs” is short: it starts the week it is due.
The start date is set in the task panel, just below the due date. Due dates can also be changed in the list view, which is quicker when you are adjusting fifteen tasks in a row.

Step 3: plan backwards from each diamond
With the diamonds and bars in place, read the chart from right to left. Everything the beta needs should end to the left of the first diamond; everything the launch needs should end to the left of the second.
In the demo this shows two things straight away. Translation work sits between the two milestones, which is right: the client asked for French and German pages for the launch, not the beta. And the three bars in progress all cross the today line, which means a lot is due in the same few days.
Step 4: look for red, then for crowding
The red bar is “Homepage hero and illustrations”. It was due on 14 November and is still in progress. On the board that is one red date among sixteen cards. On the timeline you can see what it sits next to: the checkout redesign ends a day later and the beta is a week away.
Crowding is the other thing to look for. If one person’s name is on four overlapping bars, the dates are a wish. The bars are labelled with the assignee for exactly this reason.
Step 5: deal with the unscheduled list
Tasks without dates are listed as unscheduled rather than being left off. In the demo, “Audit analytics events” in the backlog has no assignee and no date. That is a legitimate state for a backlog item, but check the list each week: a task that matters and has no date will not appear on anyone’s plan.
Weeks or months
Use Weeks while you are working inside the plan: each day is a column and a one-day slip is visible. Use Months when you show the plan to someone else, such as a client, who wants the shape and the two diamonds and not the daily detail.
What the timeline does not do
Dependencies are recorded on tasks (blocks and blocked by) but are not drawn as lines between bars. There are no sprints or burndown charts. The timeline is a picture of the dates on your tasks; keeping those dates honest is still your job.
A plan is the dates plus the habit
The whole method fits in four lines:
- Flag the fixed dates as milestones.
- Give every scheduled task a start date as well as a due date.
- Once a week, open the timeline: fix what is red, spread what is crowded, schedule or drop what is unscheduled.
- When a date changes, change it on the task and say why in a comment.
The same dates feed two other views. The calendar shows them by month across all your projects, and My tasks shows each person their own, which is the subject of the next post.